Constrained to do nothing?

glenmorieDrs. John Constable and Lee Moroney of REF on the subject:

Dear Editor: Utility Week’s article misleadingly implies that generators other than windfarms are routinely “paid to do nothing”. This is incorrect. Unlike wind, conventional generators are not paid extra when constrained off, but instead pay National Grid (because of avoided fuel cost).

The article suggests that in 2012/13, £162 million was paid to all generators not to generate, with only 4 per cent going to wind. However, Utility Week has conflated a) payments to conventional generators to increase output, and b) payments to wind to reduce output. This is confusing.

Furthermore, the article neglects to explain that its constraint cost figure consists of direct costs (including payments to wind) and indirect costs (confidential constraint contracts – some with windfarms, intertrip contracts, and the costs of replacing the constrained-off wind energy beyond a grid constraint). The conclusion that 4 per cent of the payments go to wind is incorrect since the full cost of constraining wind off is necessarily much larger.

Utility Week claims that the £7.7 million (actually £8.2 million) paid to wind power in August 2013 to reduce output was “compensation for the 91GWh they could not sell”. However, wholesale income is not lost; constraint payments (over)compensate for lost subsidy. A ROC was worth £42 in 2012 while the LEC was worth about £5. Consequently, onshore wind in 2012 could defend a compensation rate of £47/MWh. In fact, wind charged an average of £113/MWh.

Average wind constraint prices have fallen to about £88/MWh in the calendar year 2013, but are still significantly higher than the lost subsidy, with a large range from windfarm to windfarm (£72-£200/MWh). This is not in the consumer interest and suggests abuse of market power.

Contrary to the implication of Utility Week, REF has not misrepresented the constraints data. Your simplistic analysis is flawed since it covers up growing volumes of constrained wind energy, excessive wind constraint prices, and the increasing direct and indirect costs of constraining wind.

Dr John Constable (director)
Dr Lee Moroney (principal analyst)
Renewable Energy Foundation

Advertisements

About Dougal Quixote

Slightly mad. Always believes a cup is half full so continues to tilt at Wind Turbines and the politicians that seem to believe it is their god given right to ruin Scotland for a pot of fool's gold.
This entry was posted in Wind farms. Bookmark the permalink.

One Response to Constrained to do nothing?

  1. 1957chev says:

    And the miscreants are still banging them up. Prison sentences are in order.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s